LICENSEWARE

Siemens Industry Software v. Lion Global Offshore

This article is about the 2014 Singapore High Court decision enforcing a licence purchase agreed to settle a software compliance dispute. It is not legal advice.

On This Page

Siemens Industry Software Pte Ltd v. Lion Global Offshore Pte Ltd is a 2014 decision of the High Court of Singapore on the enforceability of a licence purchase that a customer signed to settle a software compliance dispute. Siemens’ Singapore software company alleged that eight copies of its software had been installed and used without authorisation on Lion Global Offshore’s computer system. At a meeting at Siemens’ office, Lion Global Offshore signed a settlement agreement and a separate agreement to buy six FEMAP licences for S$250,000 plus tax, and then refused to pay. Justice Chan Seng Onn upheld summary judgment for S$267,500, holding that the purchase agreement was a separate, binding contract.[1]

Background

The plaintiff was the Singapore company in the Siemens group whose business was software development and consultancy. The defendant was a Singapore company in offshore rig and vessel design, shipbuilding and ship repair.[1]

The parties were in dispute over the installation and use of eight allegedly infringing copies of Siemens software on the defendant’s computer system. In a letter dated 26 June 2014, the defendant’s general manager effectively admitted that there had been unauthorised installations and use, according to the court. Before the meeting, Siemens had also disclosed to the defendant a pricing mechanism from which a figure of about US$800,000 in potential damages had been derived.[1]

The dispute

On 27 June 2014 the defendant’s director and general manager met Siemens at its office, including Siemens’ director of License Compliance for Asia Pacific. Two documents were signed:[1]

Document Content 
Settlement Agreement Two pages, eight clauses. A full and final settlement of the copyright dispute on a no-fault basis. The defendant agreed to buy six sets of FEMAP under the purchase agreement, and the settlement would take effect only once all amounts under the invoice were paid in full. 
“Quotation 419833 Licensed Software Designation Agreement” Three pages. Six FEMAP licences for S$250,000 plus tax, delivery by electronic download, and the words “Valid through: June 30, 2014”. Signed by the defendant’s general manager and countersigned by Siemens. 

Siemens issued a pro forma invoice for S$267,500, including goods and services tax. On about 2 July 2014 the defendant said it would not pay. In emails afterwards, its director wrote that he had felt “the need to settle as gentlemen” under pressure and had “mistakenly agreed”, and the general manager wrote that the settlement quantum “exceeds our expectation”. Siemens treated the refusal as a repudiatory breach, but elected to perform. On 15 July 2014 it made the six licences available for download with passwords and instructions, as the purchase agreement provided, and then demanded payment. It sued for the price as a debt on 24 July 2014.[1]

An Assistant Registrar entered summary judgment for S$267,500. The defendant appealed to a High Court judge, arguing that there were six triable issues.[1]

Decision or outcome

The court dismissed the appeal and awarded Siemens S$4,000 in costs and disbursements. It noted that the defendant had filed a further appeal against that decision.[1]

Two separate agreements

The defendant argued that the purchase agreement was only an annexure to the settlement agreement, and that neither was binding until the settlement took effect. The court called this “a rather bizarre assertion”. The settlement agreement resolved the copyright dispute, while the purchase agreement was a sale of licences. The settlement depended on the purchase, but the purchase could not logically depend on the settlement, because the settlement took effect only once the purchase price was paid. Because the purchase agreement stood alone, Siemens did not have to plead the settlement agreement.[1]

Duress

The defendant’s director said that Siemens’ compliance director had warned that copyright infringement was a serious crime, had mentioned potential damages of over US$800,000, and had said Siemens would sue if there were no settlement. The court treated these assertions as an afterthought, as they had not been pleaded or argued before the Assistant Registrar. In any event, a threat made in good faith to enforce legal rights is not duress. The threats were “not without basis”, given the defendant’s admission and the pricing mechanism disclosed before the meeting. The court described the defendant’s position as “a classic case of buyer’s remorse”, in the words of Siemens’ submissions.[1]

Uncertainty and expiry

The court rejected the argument that the purchase agreement was void for uncertainty because it did not state when payment was due. The quantity, method of delivery and price were fixed, and the timing of payment was a minor term. The invoice demanding immediate payment did not vary the agreement. The words “Valid through: June 30, 2014” meant the date by which the quotation had to be accepted, not a date on which a concluded agreement would lapse if it had not been performed.[1]

Significance for software licensing and SAM practice

The decision arose on a summary judgment application and concerns contract law, not whether the defendant had actually infringed copyright. The court did not decide the underlying copyright dispute. No reported appellate decision in the case was found on the Supreme Court of Singapore’s judgment database.[1]

The case shows how a vendor’s licence compliance process can turn into a contract claim:

  • The commercial resolution becomes the claim. Siemens sued for the price of the licences under the purchase agreement, not for copyright damages, and obtained judgment without a trial.[1]
  • Settlement structure. Making the settlement conditional on a separate licence purchase meant that refusing to pay left the customer bound by the purchase but without the protection of the settlement.[1]
  • Pressure in compliance meetings. The court accepted that warnings of legal action and of potential damages, where there was a basis for them, did not make the agreement voidable.[1]
  • Admissions. The defendant’s earlier letter admitting unauthorised installations was one reason the court found the warnings were not baseless.[1]

The documents described are those signed in 2014. Siemens’ current terms on compliance checks and excess use are described in Siemens Digital Industries Software audits and usage reporting.

Lessons learned

  • A licence purchase signed to settle a compliance dispute can be enforced as a separate contract. The court held the purchase agreement binding on its own, even though the settlement never took effect because the price was not paid.[1]
  • A good-faith threat to sue over unlicensed use is not duress. The court applied the rule that a bona fide threat to enforce legal rights is not illegitimate pressure.[1]
  • Read the documents before signing at a compliance meeting. The court found that the defendant’s representatives had read both documents and knew what they were signing, and that later regret about the amount did not release the company.[1]

References

  1. Siemens Industry Software Pte Ltd v Lion Global Offshore Pte Ltd [2014] SGHC 251 (High Court of Singapore, 28 November 2014)Official text published by the Supreme Court of Singapore (eLitigation)Effective 2014-11-28. Retrieved 2026-10-01.

See also

Esc